California is unable to assure the timely construction of universal fiber to the premises (FTTP) infrastructure – estimated to cost $9.78 billion including infrastructure hardening in areas with high wildfire risk – because less than half that amount is available as federal and state subsidy funding.
That’s according to the state’s draft Five Year Action Plan required by the National Telecommunications and Information Administration’s (NTIA) Broadband Equity, Access and Deployment (BEAD) program. BEAD requires states to file “a comprehensive, high-level plan for providing reliable, affordable, high-speed internet service throughout the (state) including the estimated timeline and cost for universal service.” Additionally, the plans must include an estimated timeline and cost for universal service and planned utilization of federal, state, and local funding sources to pay for it.
“This estimate assumes no re-use of existing infrastructure (e.g., poles, conduit, manholes, etc.) in the total investment,” the draft plan prepared by the California Public Utilities Commission states. “The timeline for universal service with fiber-to-the-premises would extend beyond the BEAD funding timeline and require additional federal and state funding.”
The draft plan cautions given the Golden State’s large size, it may be challenging for BEAD-funded subgrantees to deploy infrastructure within the required five-year timeline. Additionally, “the CPUC recognizes that developing sufficient capacity may be a challenge for some potential subgrantees, including small ISPs and localities and other entities” as well as permitting challenges.
Oregon’s draft Five Year Action Plan similarly concluded that state’s BEAD funding allocation would not sufficiently subsidize universal FTTP. Like Oregon, California’s draft plan calls for the possible use of alternatives funded by the state’s $1.86 billion BEAD allocation. Those deemed “reliable” by the NTIA include hybrid fiber-coaxial cable, digital subscriber line (DSL) technology and terrestrial fixed wireless utilizing entirely licensed spectrum or using a hybrid of licensed and unlicensed spectrum.
Analysis & commentary on America's troubled transition from analog telephone service to digital advanced telecommunications and associated infrastructure deficits.
Tuesday, August 08, 2023
California BEAD Five Year Action Plan: Substantially greater funding needed for universal FTTP.